WIP Phase 2C
  • 1st January 2024: Final touch-up work at Level 8 is currently in progress
  • 1st December 2023: Landscaping Level 8: Planting and hardscape works in progress
  • 1st October 2023: Now in progress 2nd tier facade level 30
  • 1st September 2023: Tower in progress casting slab level 26
  • 1st August 2023: Tower in progress casting slab level 26
  • 1st July 2023: Tower in progress casting slab level 23
  • 1st June 2023: Tower in progress casting slab level 19
  • 1st May 2023: Tower in progress casting Level 15
  • 1st April 2023: Overall view. Formwork at Level 12 in progress.
  • 1st March 2023: Casting SLAB Level 10 in progress
  • 1 February 2023 : In progress casting slab for Level 9
  • 1 January 2023 : Level 9 in progress
  • 1 December 2022 : Casting slab level 8 in progress
  • 1 November 2022 : Park Homes in progress casting floor slab for level 4
  • 1 October 2022 : Car park in progress concreting at level 6 and ParkHomes at level 4
  • 1 September 2022 : Carpark - level 6 works in progress
  • 1 August 2022: Level 4 parking slab & Parkhomes level 2 shear wall in progress
  • 1 JUNE 2022: 2nd Floor Slab in Progress
  • 2 MARCH 2022: 1st Floor Structure in Progress
  • 4 Jan 2022: Superstructure Work in Progress
  • 25 NOV 2021
  • 27 OCT 2021: UNDERGROUND WORK IN PROGRESS
  • 25 Aug 2021
  • 18 May 2021: Commencement of superstructure work
  • 5 April 2021: Piling work in progress

Disclaimer: Any sketches, illustrations, renderings, images, pictures, amenities, food services, unit finishes, plans, specifications, art and/or visuals shown and featured in this website including the interior design concepts, colour schemes and suggested furnishings in the completed unit/development are artist’s impression only and shall not be taken as a representation of fact. Whilst every reasonable care has been taken in providing this information the developer shall not be held responsible for any inaccuracy and changes as may be required by the authorities.